Tag Archives: European Pressurized Reactor (EPR)

Olkiluoto 3 Nuclear Plant is Ready: 2005-2020

Finland’s Radiation and Nuclear Safety Authority (Stuk) yesterday informed the government it sees no reason why an operating licence for the first-of-a-kind nuclear plant EPR at Olkiluoto 3 should not be granted to utility Teollisuuden Voima Oyj (TVO).]…The Areva-Siemens consortium began construction of Olkiluoto 3 – the first-of-a-kind EPR – in 2005 under a turnkey contract signed with TVO in late 2003. Completion of the reactor was originally scheduled for 2009, but the project has suffered various delays and setbacks. Under the latest schedule, fuel will now be loaded into the reactor core in June 2019, with grid connection to take place in October 2019, and the start of regular electricity generation scheduled for January 2020.

In December 2018, unit 1 of the Taishan plant in China’s Guangdong province became the first EPR to enter commercial operation. Taishan 2 is scheduled to begin commercial operation in 2019. The loading of fuel into the core of the Flamanville EPR in France is expected towards the end of this year. Two EPR units are also under construction at the Hinkley Point C project in Somerset, UK.

Excerpts from Regulator concludes Finnish EPR can operate safely, Nuclear News, Feb. 2019

Nuclear Power in Abu Dhabi

The Barakah nuclear-power plant under construction in Abu Dhabi will never attract the attention that the Burj Khalifa skyscraper in neighbouring Dubai does, but it is an engineering feat nonetheless. It is using three times as much concrete as the world’s tallest building, and six times the amount of steel. Remarkably, its first reactor may start producing energy in the first half of this year—on schedule and (its South Korean developers insist) on budget. That would be a towering achievement.

In much of the world, building a nuclear-power plant looks like a terrible business prospect. Two recent additions to the world’s nuclear fleet, in Argentina and America, took 33 and 44 years to erect. Of 55 plants under construction, the Global Nuclear Power database reckons almost two-thirds are behind schedule .  The delays lift costs, and make nuclear less competitive with other sources of electricity, such as gas, coal and renewables.

Not one of the two technologies that were supposed to revolutionise the supply of nuclear energy—the European Pressurised Reactor, or EPR, and the AP1000 from America’s Westinghouse—has yet been installed, despite being conceived early this century. In Finland, France and China, all the EPRs under construction are years behind schedule. The main hope for salvaging their reputation—and the nuclear business of EDF, the French utility that owns the technology—is the Hinkley Point C project in Britain, which by now looks a lot like a Hail Mary pass.

Meanwhile, delays with the Westinghouse AP1000 have caused mayhem at Toshiba, its owner. The Japanese firm may announce write-downs in February of up to $6bn on its American nuclear business. As nuclear assets are probably unsellable, it is flogging parts of its core, microchip business instead.

This month, Oregon-based NuScale Power became the first American firm to apply for certification of a small modular reactor (SMR) design with America’s nuclear regulators.

“Clearly the momentum seems to be shifting away from traditional suppliers,” says William Magwood, director-general of the OECD’s Nuclear Energy Agency. Both small and large reactors are required. In places like America and Europe, where electricity demand is growing slowly, there is rising interest in small, flexible ones. In fast-growing markets like China, large nuclear plants make more economic sense.

If the South Koreans succeed with their first foreign nuclear programme in Abu Dhabi, the reason is likely to be consistency. Nuclear accidents such as Three-Mile Island in 1979 and Chernobyl in 1986 caused a long hiatus in nuclear construction in America and Europe. But South Korea has invested in nuclear power for four decades, using its own technology since the 1990s, says Lee Jong-ho, an executive at Korea Electric Power (KEPCO), which leads the consortium building Barakah. It does not suffer from the skills shortages that bedevil nuclear construction in the West.

KEPCO always works with the same, familiar suppliers and construction firms hailing from Korea Inc. By contrast, both the EPR and AP1000, first-of-a-kind technologies with inevitable teething problems, have suffered from being contracted out to global engineering firms. Also, South Korea and China both keep nuclear building costs low through repetition and standardisation, says the World Nuclear Association (WNA), an industry group. It estimates that South Korean capital costs have remained fairly stable in the past 20 years, while they have almost tripled in France and America.

Excerpts The nuclear options: How to build a nuclear-power plant, Economist, Jan. 28 2017, at 57

 

Nuclear Industry: France, Russia and China

[Regarding the French nuclear company Areva] its newest product, the expensive European Pressurised Reactor (EPR), has encountered more than the teething problems common to all big industrial projects. A plant in Finland is almost ten years behind schedule and almost three times over budget: Areva has had to write off billions as a result….Two reactors in China and the only new-build in France, at Flamanville, are also running late. EDF played an important role in managing the Chinese and French projects.

Besides criticism for slack project management, Areva and EDF (Electricite de France) have been questioned over technical standards. The steel in the main reactor vessel at Flamanville is faulty, the Nuclear Safety Authority said in April 2015. EDF disputes the finding and, with Areva, has started new tests. The news added to growing disenchantment in Britain with an agreement, not yet firm, that expensively entrusts the construction of a power station incorporating two Areva EPRs to a consortium led by EDF.  It seems unlikely that Areva will find many more foreign takers for its existing reactor…

[S]ome of Areva’s rivals are racing ahead. Rosatom, a Russian nuclear firm, has built up a fat order-book. Keen pricing, generous financing and relaxed technology transfer help, though Western sanctions do not. China’s two reactor-builders, CNNC and CGN, are peddling their own new design, Hualong One; in February CNNC signed a preliminary agreement to supply a reactor to Argentina.

Areva has little reason to hope for a surge of new orders at home. France’s 58 reactors are elderly but EDF, which operates them, plans to revamp rather than replace them…A new law set to come into force this summer, pledging somehow to cut France’s dependence on nuclear power from 75% to 50% of its electricity needs by 2025, will make Areva’s prospects even bleaker.

Excerpts from France’s nuclear industry: Arevaderci, Economist, May 23, 2015, at 53.