Tag Archives: nuclear waste Japan

Lots of Money Forever for Waste that Lasts for Forever: Nuclear Waste in Japan

Since August 2020, two local governments on the western shore of Hokkaido in Japan have said they will apply to the central government for a survey that could eventually lead to their municipalities hosting a permanent underground repository for high-level radioactive waste. The fact that these two localities made their announcements about a month apart and are situated not far from each other was enough to attract more than the usual media attention, which revealed not only the straitened financial situations of the two areas, but also the muddled official policy regarding waste produced by the country’s nuclear power plants.

The respective populations of the two municipalities reacted differently. The town of Suttsu made its announcement in August 2020, or, at least, its 71-year-old mayor did, apparently without first gaining the understanding of his constituents, who, according to various media, are opposed to the plan…. Meanwhile, the mayor of the village of Kamoenai says he also wants to apply for the study after the local chamber of commerce urged the village assembly to do so in early September 2020. TBS asked residents about the matter and they seemed genuinely in favor of the study because of the village’s fiscal situation. Traditionally, the area gets by on fishing — namely, herring and salmon — which has been in decline for years. A local government whose application for the survey is approved will receive up to ¥2 billion in subsidies from the central government… Kamoenai, already receiving subsidies for nuclear-related matters. The village is 10 kilometers from the Tomari nuclear power plant, where some residents of Kamoenai work. In exchange for allowing the construction of the plant, the village now receives about ¥80 million a year, a sum that accounts for 15 percent of its budget. According to TBS, Kamoenai increasingly relies on that money as time goes by, since its population has declined by more than half over the past 40 years.

Since Japan’s Nuclear Waste Management Organization started soliciting local governments for possible waste storage sites in 2002, a few localities have expressed interest, but only one — the town of Toyo in Kochi Prefecture — has actually applied, and then the residents elected a new mayor who canceled the application. The residents’ concern was understandable: The waste in question can remain radioactive for up to 100,000 years.

The selection process also takes a long time. The first phase survey, which uses existing data to study geological attributes of the given area, requires about two years. If all parties agree to continue, the second phase survey, in which geological samples are taken, takes up to four years. The final survey phase, in which a makeshift underground facility is built, takes around 14 years. And that’s all before construction of the actual repository begins.

Neither Suttsu nor Kamoenai may make it past the first stage. Yugo Ono, an honorary geology professor at Hokkaido University, told the magazine Aera that Suttsu is located relatively close to a convergence of faults that caused a major earthquake in 2018. And Kamoenai is already considered inappropriate for a repository on a map drawn up by the trade ministry in 2017.

If the Nuclear Waste Management Organization’s process for selecting a site sounds arbitrary, it could reflect the government’s general attitude toward future plans for nuclear power, which is still considered national policy, despite the fact that only three reactors nationwide are online.

Japan’s spent fuel is being stored in cooling pools at 17 nuclear plants comprising a storage capacity of 21,400 tons. As of March 2020, 75 percent of that capacity was being used, so there is still some time to find a final resting place for the waste. Some of this spent fuel was supposed to be recycled at the Rokkasho Reprocessing Plant in Aomori Prefecture, but, due to numerous setbacks, it doesn’t look as if it’s ever going to open, so the fuel will just become hazardous garbage.

According to some, the individual private nuclear plants should be required to manage their own waste themselves. If they don’t have the capacity, then they should create more. It’s wrong to bury the waste 300 meters underground because many things can happen over the course of future millennia. The waste should be in a safe place on the surface, where it can be readily monitored.  However, that would require lots of money virtually forever, something the government would prefer not to think about, much less explain. Instead, they’ve made plans that allow them to kick the can down the road for as long as possible.

Excerpt from PHILIP BRASOR, Hokkaido municipalities gamble on a nuclear future, but at what cost? Japan Times, Oct. 24, 2020

What to Do with 56 000 Drums of Nuclear Waste: Japan

At least 1.9 trillion yen ($17.12 billion) will be needed for the planned scrapping of 79 nuclear facilities, including the failed Monju prototype fast-breeder reactor, according to the Japan Atomic Energy Agency (JAEA).

However, the JAEA’s estimate, released on Dec. 26, 2018 does not include maintenance expenses for the facilities nor costs to deal with leftover uranium and plutonium, meaning the actual tally could increase by hundreds of billions of yen.  State subsidies account for the bulk of the JAEA’s budget, so taxpayers will likely foot most of the bill.  The agency plans to shut down 79 of its 89 nuclear facilities, including research reactors and test buildings, over 60 to 70 years due to aging and the huge costs needed for their continued operations under stricter safety standards.

According to the JAEA’s estimate, the cost to decommission the Tokai spent nuclear fuel reprocessing plant in Ibaraki Prefecture will be 770 billion yen.  But the overall cost would reach nearly 1 trillion yen if expenses on dealing with highly radioactive liquid waste, which is left after plutonium is extracted from spent fuel rods at the plant, are included.

The problem-plagued Monju prototype fast-breeder reactor in Tsuruga, Fukui Prefecture, cost taxpayers more than 1 trillion yen ($8.82 billion) despite running for only 250 days during its two-decade operation. ..But the JAEA currently has no plan on how to handle plutonium stored at the facilities. In addition, no decision has been made on what to do with radioactive waste from the 79 facilities that could fill more than 560,000 200-liter drums.

Excerpt JAEA: Closing 79 nuclear facilities will cost at least 1.9 trillion yen
THE ASAHI SHIMBUN, Dec. 27 2018

Japan’s Nuclear Waste

Japan seeks final resting place for highly radioactive nuclear waste…[W]ith a number of Japan’s nuclear reactors closed down for good in the wake of the Fukushima accident, the need for a permanent storage site is more pressing than ever.

The disaster, in which a 13-meter tsunami triggered by an off-shore earthquake crippled four reactors at the plant and caused massive amounts of radioactivity to escape into the atmosphere, also underlined just how seismically unstable the Japanese archipelago is and the need for the repository to be completely safe for 100,000 years.

“They have been trying to get this plan of the ground for years and one thing they tried was to offer money to any town or village that agreed to even undergo a survey to see if their location was suitable,” she said.  “There were a number of mayors who accepted the proposal because they wanted the money – even though they had no intention of ever agreeing to host the storage site – but the backlash from their constituents was fast and it was furious,” Smith added.  “In every case, those mayors reversed their decisions and the government has got nowhere,” she said. “But I fear that means that sooner or later they are just going to make a decision on a site and order the community to accept it.”

The security requirements of the facility will be exacting, the government has stated, and the site will need to be at least 300 meters beneath the surface in a part of the country that is not subject to seismic activity from active faults or volcanoes. It must also be safe from the effects of erosion and away from oil and coal fields. Another consideration is access and sites within 20 km of the coast are preferred.

The facility will need to be able to hold 25,000 canisters of vitrified high-level waste, while more waste will be produced as the nation’s nuclear reactors are slowly brought back online after being mothballed since 2011 for extensive assessments of their safety and ability to withstand a natural disaster on the same scale as the magnitude-9 earthquake that struck Fukushima.

When it is released, the government’s list is likely to include places in Tohoku and Hokkaido as among the most suitable sites, because both are relatively less populated than central areas of the country and are in need of revitalization efforts. Parts of Tohoku close to the Fukushima plant may eventually be chosen because they are still heavily contaminated with radiation from the accident.

Excerpts from Japan seeks final resting place for highly radioactive nuclear waste, Deutsche Welle, May 4, 2017

Why Japan Likes its Monju: nuclear reactors

Monju  is a Japanese sodium-cooled fast reactor, located in Tsuruga Nuclear Power Plant, Fukui Prefecture..  Monju is a sodium cooled, MOX-fueled, loop-type reactor with three primary coolant loops…The reactor has been inoperative for most of the time since it has been built [due to accidents and resulting public suspicion].  On December 8, 1995, the reactor suffered a serious accident. Intense vibration caused a thermowell inside a pipe carrying sodium coolant to break… [T]he sodium was not radioactive. However, there was massive public outrage in Japan when it was revealed that Power Reactor and Nuclear Fuel Development Corporation (PNC), the semigovernmental agency then in charge of Monju, had tried to cover up the extent of the accident and resulting damage. This coverup included falsifying reports and the editing of a videotape taken immediately after the accident, as well as issuing a gag order that aimed to stop employees revealing that tapes had been edited.

More  Problems

On 16 February 2012 Nuclear and Industrial Safety Agenbcy reported that a sodium-detector malfunctioned.  On 30 April 2013 an operating error rendered two of the three emergency generators unusable.  On Monday 16 September 2013 before 3 a.m. the data transmission of the reactor stopped to the government’s Emergency Response Support System.

Excerpts from Wikipedia

A panel of experts set up by the Education, Culture, Sports, Science and Technology Ministry has begun discussions on what should be done about the Monju reactor. The panel is expected to reach a conclusion by the summer 2016.  Since 2012, the Nuclear Regulation Authority (NRA) has repeatedly conducted on-the-spot inspections of Monju, which is now operated by the Japan Atomic Energy Agency (JAEA). Every time these inspections were conducted, however, they have identified faulty maintenance checks of the reactor and others that violated related laws and regulations.,Monju’s maintenance and inspection program was drawn up in 2009. What is a serious issue is the program had a large number of defects.About 50,000 pieces of equipment must be inspected at the reactor. Without a carefully thought-out plan, these inspections will be far from smooth. It is crucial to review the maintenance and inspection plan, which is the foundation for ensuring safety…

Under the government’s Strategic Energy Plan, Monju is considered a key research base to reduce the volume of nuclear waste. The development of nuclear reactors similar to Monju is under way in Russia, China and India, as uranium resources can be effectively utilized with the fast breeder reactor.Can Japan afford to stop development of the fast breeder reactor and let these countries lead the way? This is indeed a crucial moment.

New organization needed to regain public trust in Monju management, The Yomiuri Shimbun, Jan 18, 2015

Nuclear Waste from Britain to Japan on the Pacific Grebe

Japan Nuclear Fuel Ltd. said Thursday that 28 canisters of high-level radioactive waste produced through the reprocessing of spent Japanese nuclear fuel in Britain will arrive in Aomori Prefecture in the latter half of February.  The 28 canisters of vitrified radioactive waste include 14 for Kansai Electric Power Co. and seven each for Chubu Electric Power Co. and Chugoku Electric Power Co.

The freighter Pacific Grebe carrying the waste left the port of Barrow on Wednesday Jan, 9, 2013) and will travel to Rokkasho, Aomori Prefecture, via the Panama Canal, Japan Nuclear Fuel said.  It will be the third time that vitrified radioactive waste will be brought to Japan from Britain.

Japan has received 104 canisters of such waste from Britain and plans to receive around 800 more. The 104 canisters have been stored at a facility in the village of Rokkasho.

Reprocessed nuclear waste to arrive in Aomori from Britain in late February, The Japan Times, Jan. 11, 2012

Illegal Nuclear Waste Dumping, Japan

Cleanup crews in Fukushima Prefecture have dumped soil and leaves contaminated with radioactive fallout into rivers. Water sprayed on contaminated buildings has been allowed to drain back into the environment. And supervisors have instructed workers to ignore rules on proper collection and disposal of the radioactive waste.  Decontamination is considered a crucial process in enabling thousands of evacuees to return to their homes around the crippled Fukushima No. 1 nuclear power plant and resume their normal lives.  But the decontamination work witnessed by a team of Asahi Shimbun reporters shows that contractual rules with the Environment Ministry have been regularly and blatantly ignored, and in some cases, could violate environmental laws.  “If the reports are true, it would be extremely regrettable,” Fukushima Governor Yuhei Sato said at his first news conference of the year on Jan. 4. “I hope everyone involved will clearly understand how important decontamination is to the people of Fukushima.”

He called on the Environment Ministry to investigate and present a clear report to the prefectural government.  The shoddy practices may also raise questions about the decontamination program itself–and the huge amounts of money pumped into the program.  The central government initially set aside 650 billion yen ($7.4 billion) to decontaminate areas hit by radioactive substances from the March 11, 2011, accident at the Fukushima plant. Since last summer, the Environment Ministry has designated 11 municipalities in Fukushima Prefecture for special decontamination work.  Work has already begun in four municipalities to remove radioactive substances from areas within 20 meters of buildings, roads and farmland.  The Environment Ministry itself does not have the know-how to decontaminate such a large area, so it has given contracts to joint ventures led by major construction companies to do the work.

A contract worth 18.8 billion yen to decontaminate the municipality of Naraha was awarded to a group that includes Maeda Corp. and Dai Nippon Construction. A 7.7-billion-yen contract for Iitate was signed with a group that includes Taisei Corp., while a 4.3-billion-yen contract for Kawauchi was given to a group led by Obayashi Corp. A consortium that includes Kajima Corp. was awarded a 3.3-billion-yen contract to clean up Tamura.  In signing the contracts, the Environment Ministry established work rules requiring the companies to place all collected soil and leaves into bags to ensure the radioactive materials would not spread further. The roofs and walls of homes must be wiped by hand or brushes. The use of pressurized sprayers is limited to gutters to avoid the spread of contaminated water. The water used in such cleaning must be properly collected under the ministry’s rules.

A special measures law for dealing with radioactive contamination of the environment prohibits the dumping of such waste materials. Violators face a maximum prison sentence of five years or a 10-million-yen fine.  From Dec. 11 to 18, four Asahi reporters spent 130 hours observing work at various locations in Fukushima Prefecture.At 13 locations in Naraha, Iitate and Tamura, workers were seen simply dumping collected soil and leaves as well as water used for cleaning rather than securing them for proper disposal. Photographs were taken at 11 of those locations.

Excerpt, CROOKED CLEANUP (1): Radioactive waste dumped into rivers during decontamination work in Fukushima, THE ASAHI SHIMBUN, Jan. 4, 2012